The Hornsea Two Offshore Wind Farm Order

The Hornsea Two Offshore Wind Farm Order

Published: 16 February 2018

SECTION 153 OF THE PLANNING ACT 2008
REGULATION 6 OF THE INFRASTRUCTURE PLANNING (CHANGES TO, AND
REVOCATION OF, DEVELOPMENT CONSENT ORDERS) REGULATIONS 2011
NOTICE OF APPLICATION TO MAKE A NON MATERIAL CHANGE TO THE FOLLOWING DEVELOPMENT CONSENT ORDER:

The Hornsea Two Offshore Wind Farm Order 2016 (SI 2016: 844 as amended by SI 2016 No. 1104)

An application has been made by Optimus Wind Limited and Breesea Limited (“the Applicant”) to the Secretary of State to make a non-material amendment to the above-mentioned Development Consent Order (“DCO”). The contact address of the Applicant is: Optimus Wind Limited / Breesea Limited, 5 Howick Place, London SW1P 1WG.

The contact details of the project manager are: Natasha Litten, Optimus Wind Limited / Breesea Limited, 5 Howick Place, Victoria, London SW1P 1WG.
Email: NATLI@orsted.co.uk Tel: +44 207 811 5200.

The application seeks to make changes to the DCO which are not material. The changes are: an amendment to paragraphs 3(1) and 3(2) of Part 1 (Authorised Development) of Schedule 1 (Authorised Project) in respect of Works Nos. 2A and 2B to reduce the permitted maximum number of offshore HVAC collector substations from 6 to 3; amendments to paragraph 2(4) of Part 3 (Requirements) of Schedule 1 (Authorised Project) to amend the maximum area of each HVAC collector substation platform by substituting the figure of 3,600 square metres with the figure of 6,300 square metres and to amend the maximum width of each HVAC collector substation platform by substituting the figure of 60 metres with the figure of 90 metres.

The application documents are available for inspection free of charge at:
Grimsby Central Library, Town Hall Square, Grimsby, DN31 1HG: Opening Hours: Monday to Friday – 8.30am - 7.30pm and Saturday – 9am - 1pm. Closed Sunday.
Mablethorpe Library, Stanley Avenue, Mablethorpe, Lincolnshire, LN12 1DP. Opening hours Monday to Friday 9am - 5pm (6pm on Thursday only), Saturday 9am – 1pm. Closed Sunday.

The latest date the application documents will be available for inspection is 26th March 2018.

The application documents are also available to view online at the following web address: http://infrastructure.planninginspectorate.gov.uk/projects/yorkshire-and-the-humber/hornsea-offshore-wind-farm-zone-4-project-two/

A free digital copy of the application can be obtained from the Applicant using the contact details provided above. Alternatively, a paper copy can be obtained from the Applicant for free. Copying facilities are also available at the above noted libraries (at a cost of 10 pence per sheet).

Please send any representations about the application by email to the Secretary of State c/o the Planning Inspectorate at Hornsea2@pins.gsi.gov.uk, or in writing to: Major Applications and Plans, The Planning Inspectorate, Temple Quay House, Temple Quay, Bristol BS1 6PN. Representations will be made public by being published on the Planning Inspectorate’s website.

The Planning Inspectorate will co-ordinate the receipt of any representations and will pass to the Applicant a copy of any representations received unless the person or persons making the representations expressly request that their comments should not be copied to the Applicant.

The deadline for the receipt of representations on the application is 5pm on 26th March 2018.