DONG ENERGY WIND POWER A/S

DONG ENERGY WIND POWER A/S

Published: 30 August 2017

DONG ENERGY WIND POWER A/S

THE ENERGY ACT 2004

NOTICE OF APPLICATION FOR SAFETY ZONE SCHEME DURING CONSTRUCTION AND
MAJOR MAINTENANCE OF THE HORNSEA PROJECT ONE OFFSHORE WIND FARM

THE ELECTRICITY (OFFSHORE GENERATING STATIONS) (SAFETY ZONES) (APPLICATION
PROCEDURES AND CONTROL OF ACCESS) REGULATIONS 2007 – STATUTORY INSTRUMENT
2007 NO 1948


Notice is hereby given that DONG ENERGY WIND POWER A/S (a company registered in Denmark (company
number CVR 31849292, with its registered office at Kraftværksvej 53 Skærbæk 7000 Fredericia, Denmark) have
applied for consent from the Secretary of State for Business, Energy, and Industrial Strategy (BEIS) as set out in
the Energy Act 2004 and the Electricity (Offshore Generating Stations) (Safety Zones) (Application Procedures
and Control of Access) Regulations 2007 (SI No 2007/1948) for safety zones as detailed below, for the consented
Hornsea Project One Offshore Wind Farm, during construction and periods of major maintenance.

The following safety zones will be applied for:

• 500 metre (m) “rolling” safety zones around any wind turbine or offshore substation (including any associated
or partially constructed infrastructure, e.g., foundations) whilst work is underway at that structure, as
indicated by the presence of construction vessels.

• 500m safety zones around permanently manned jacked up accommodation platforms within the consent
boundary during the construction phase.

• 50m pre-commissioning zones around any completed wind turbine or offshore substation prior to final
commissioning.

• 500m safety zones around any wind turbine or offshore substation where major maintenance is being
undertaken during the operational phase (as indicated by the presence of a large vessel, e.g., heavy lift vessel,
jack up vessel).

The precise start date and co-ordinates of the safety zones will be detailed in the Notice to Mariners prior to the
commencement of any construction and major maintenance operations. Copies of the safety zone scheme may
be obtained by contacting BRYBR@dongenergy.co.uk, +4599515470.

Any person wishing to make representations to the Secretary of State about the application should do so in
writing to the Secretary of State, c/o Rob Pridham, Energy Infrastructure Planning Team, Department for
Business, Energy and Industrial Strategy, Orchard 2, Level 3, 1 Victoria Street, London SW1A 0ET, beiseip@beis.
gov.uk
, stating the name of the proposal and nature of their representations, not later than 28 days from the
date or latest date of publication of the notice.