This site is operated by a business or businesses owned by Maritime Insights & Intelligence Limited, registered in England and Wales with company number 13831625 and address c/o Hackwood Secretaries Limited, One Silk Street, London EC2Y 8HQ, United Kingdom. Lloyd’s List Intelligence is a trading name of Maritime Insights & Intelligence Limited. Lloyd’s is the registered trademark of the Society Incorporated by the Lloyd’s Act 1871 by the name of Lloyd’s.

This copy is for your personal, non-commercial use. For high-quality copies or electronic reprints for distribution to colleagues or customers, please call UK support at +44 (0)20 3377 3996 / APAC support at +65 6508 2430

Printed By

UsernamePublicRestriction

Coronavirus: Chinese yards braced for ‘heavy blow’

Only 50% of the workers at three major CSSC yards have returned to work amid the impact of the spreading disease, while the ratio at their smaller peers may be even lower. No wonder Cansi, China’s shipbuilding association, is warning of the risk of delivery failures

It is time for Chinese shipyards to review some of its long-term customers with the old saying that a friend in need is a friend indeed

WITH the coronavirus fears, you may wonder how many shipyard workers in China have returned to their positions after the holiday extension.

At three of the country’s largest — Shanghai Waigaoqiao Shipbuilding, Hudong-Zhonghua Shipbuilding and Jiangnan Shipyard — the turnout ratio is only 50%, state news agency Xinhua reported today.

Even so, this figure is likely to be better than lots of their domestic peers. As the major units under state conglomerate China State Shipbuilding Corp, the trio are equipped with abundant anti-virus provisions. And an array of vessels on their orderbook make them high on the government agenda that seeks to minimise economic impact while curbing infection.

Jiangnan, for example, was said to have prepared more than 500 isolated rooms to quarantine suspected patients. By comparison, some smaller privately-run yards cannot even garner enough facemasks.

Nevertheless, delays in delivery seem inevitable, even for the big players.

Chen Jun, general manager of Hudong-Zhonghua, told China Ship News, an internal publication of CSSC, that schedules of the company’s 18 vessels being built (including a number of ultra-large containerships and large liquefied natural gas carriers) are affected by the disease outbreak.

What is worse, some newbuilding contracts may be scrapped for regulatory reasons.

In an advisory to member companies on Tuesday, the country’s shipbuilding association, known as Cansi, warned of the incompliance risks in relation to the Goal-Based Standards.

Most dry bulkers and tankers over 150 m long whose shipbuilding contracts were signed on or after July 1, 2016; or whose keels were laid on or after July 1, 2017; or whose delivery is made on or after July 1, 2020 must meet the high-level vessel standards stipulated by the International Maritime Organization.  

But some of these non-GBS ships at Chinese yards that are reeling from the virus onslaught may fail to beat the delivery deadline this year, said Cansi.

These vessels will be required to make changes in designs and construction and “may enter a severe situation where they cannot be delivered”, the group added.

Recommendations by Cansi include timely reports to the shipowners and seeking protection from force majeure or “Act of God” clauses.

The same advice has also been given to domestic ship repair yards that are also feeling the impact of the epidemic. This is revealed in a recent Cansi survey over 200 ship repairing/retrofitting projects in China.

Foreign owners are behind more than 90% of these projects, and they do not appear to compromise easily.

Less than 1.5% of the owners have modified the contracts to ensure the fulfillment, the results showed, while the other 1.5% explicitly rejected the force majeure argument. The remaining majority have shown sympathy, yet are lacking commitment.

A bigger trouble will derive from “a tradition” between yards and their “old friend customers” that the contract for repairing a single ship is normally signed upon the delivery, Cansi noted. The situation obviously will leave many Chinese yards unprotected if the owners choose to walk away from delayed projects.

It is time to review the old saying: a friend in need is a friend indeed.

But Cansi seems not to be optimistic. It has asked the repair yards to be braced for a “heavy blow” in the coming three months.

Related Content

Topics

UsernamePublicRestriction

Register

LL1131005

Ask The Analyst

Please Note: You can also Click below Link for Ask the Analyst
Ask The Analyst

Your question has been successfully sent to the email address below and we will get back as soon as possible. my@email.address.

All fields are required.

Please make sure all fields are completed.

Please make sure you have filled out all fields

Please make sure you have filled out all fields

Please enter a valid e-mail address

Please enter a valid Phone Number

Ask your question to our analysts

Cancel